A: The specification stipulates that for cast-in-place concrete beams and slabs with a span of not less than 4m, the film faced shuttering plywood should be arched according to the design requirements; when the design does not have specific requirements, the 12mm shuttering ply height of the arch should be 1/1000~3/1000 of the span.